Bruce Blumberg, Associate Dean
Administration Building Room 214 (803) 938-3838
Instructional Laboratories Building
|
BUDGET
|
$11,825,000 (estimate)
|
Return to top of page.
|
|
SCOPE
|
Construction of a new 40,000 square foot building to house the Math,
Science and Engineering Division. The building is envisioned to include
lecture rooms, science laboratories, art laboratory, and faculty offices.
|
|
STATUS
|
A building committee has been established to discuss the preliminary
design requirements and is ready to resume more detail work when the funds
become available. The request for state funding (Capital Improvement Bonds)
has been sent to Columbia as part of our Comprehensive Permanent Improvement
Plan (CPIP). This project remains the top priority in new construction
on campus.
|
Deferred Maintenance Projects ($860,963)
BUDGET |
$170,000 |
Return to top of page. |
SCOPE |
HVAC replacement - Student Union Building. Replace existing duct system,
thermostats and control boxes with new equipment. |
STATUS |
Deferred Maintenance Budget, project is being
evaluated. Decision July 2007. |
| |
BUDGET |
$300,000 |
Return to top of page. |
SCOPE |
Re-roof Schwartz and Nettles Buildings. Apply a sprayed
polyurethane foam (PUF) roofing material. |
STATUS |
Completed 9/1/06. |
| |
BUDGET |
$242,000 |
Return to top of page. |
SCOPE |
Schwartz and Nettles Buildings. Remove a pneumatic controls
and upgrade to DDC. |
STATUS |
May 2007 completion date anticipated. |
| |
BUDGET |
$12,163 |
Return to top of page. |
SCOPE |
Schwartz Building - Install new carpet in classrooms. |
STATUS |
Life Sciences Bond. Completed 12/2006. |
| |
BUDGET |
$63,700 |
Return to top of page. |
SCOPE |
Science, Business Administration, Student Union, Schwartz and Nettles Buildings.
Paint exterior of buildings including soffits and columns. Also paint interior gymnasium. |
STATUS |
Completed 08/2006 |
| |
BUDGET |
$48,100 |
Return to top of page. |
SCOPE |
Campus wide Fire Alarm Upgrade. Create a fiber network. |
STATUS |
Deferred Maintenance Budget, bid process to begin May 2007. |
BUDGET |
$25,000 |
Return to top of page. |
SCOPE |
Campus wide Sidewalk Repair and Handicapped Ramps. Repair broken
sidewalks and add ramps at entrances to Science and Business Administration Buildings. |
STATUS |
Deferred Maintenance Budget, bid process to begin May 2007. |
| |
|
|
Return to top of page. |
Old Science Building Renovation
|
BUDGET
|
$1,348,000 (estimate)
|
Return to top of page.
|
|
SCOPE
|
Renovate the existing Science Building to effectively utilize the total
space available. With the construction of a new Instructional Laboratories
Building, the old Science Building can be completely renovated into a
general classroom building.
|
|
STATUS
|
The timetable for this project is totally dependent on the construction
of other permanent buildings. A starting date cannot be projected at this
time.
|
Facilities Management Center
|
BUDGET
|
$675,000
|
Return to top of page.
|
|
SCOPE
|
Construction of a 15,000 Sq. Ft. facility to house the maintenance functions,
shipping and receiving, warehouse, storage, as well as other facilities
service functions.
|
|
STATUS
|
The timetable for this project is totally dependent on the construction
of other permanent buildings. A starting date cannot be projected at this
time.
|
Please contact Bruce Blumberg Associate Dean for Administrative and Financial Services concerning questions or comments.
|